GK Development, Inc. v. Iowa Malls Financing Corporation

Illinois Appellate Court
Civil Court
Contracts
Citation
Case Number: 
2013 IL App (1st) 112802
Decision Date: 
Thursday, December 19, 2013
District: 
1st Dist.
Division/County: 
Cook Co., 4th Div.
Holding: 
Affirmed in part and reversed in part with instructions.
Justice: 
HOWSE
Contract provision for sale of four shopping centers, which required that $4.3 million of purchase price be held in escrow from seller’s proceeds then be paid to seller only if certain conditions are timely met, is unenforceable as a penalty. Provision fails to distinguish between a minor delay in permit approval and a complete failure of construction project, and thus it sought to award entire value of contract for a temporary delay, which is an unenforceable penalty to coerce performance, and a windfall to the buyer, rather than a valid liquidated damages provision. (FITZGERALD SMITH and LAVIN, concurring.)